Department of Transportation workers were busy Wednesday installing a modular structure to replace the Pecks Cove bridge.
Lisa Parsons, DTI assistant district engineer told Tantramar council on Monday that once the temporary bridge is in place, workers will build the road up on either side and put a floor on the structure. She said it should be open to fire trucks and other emergency vehicles within a week or two.
She added that DTI plans to open the bridge to the public by December 19th.
The temporary, modular bridge is parallel to the old one that could no longer bear the weight of emergency vehicles putting residents of Rockport at risk.
Route 940
Parsons’ report came during a DTI presentation to council that included updates on the status of other projects within Tantramar including the resurfacing of Rte. 940.
She said that DTI has put the project forward, but it has not been approved yet.
Ward 4 Councillor Kristen LeBlanc referred to a big increase in traffic on the road since NB Power announced that a 500 MW gas/diesel plant would be built near Centre Village.
She asked if DTI was conducting an analysis, adding that people in her ward are really worried about the road’s worsening condition.
“Route 940 is falling apart as it is,” she said, “and with the vegetation growth that we consistently call about to be taken care of, there’s really no place for vehicles to pull over.”
She added that emergency service vehicles cannot pull over because the side of Rte. 940 is crumbling and she wondered what it would take to get the road resurfacing approved.
Parsons responded that DTI has 18,000 kilometres of roads to look after in the province and projects must be done within each district’s budget.
“We have put it forward as a priority for the district to move forward,” she said, adding that DTI is currently working on Rte. 955 — a road that runs near the Confederation Bridge and Murray Beach Provincial Park.
Wheaton Covered Bridge
Parsons said that the modular structure that will run parallel to the Wheaton Covered Bridge is still in the design stage.
“Everything is looking good to be able to put it out to tender for next year,” she said.
“It will be a double-lane modular, so it will be wide enough for the farmers to take their equipment across and once that goes to tender, then timelines are up to the contractor,” she added.
“Can you give any timeline on that Lisa?” Mayor Wiggins-Colwell asked.
“There’s a lot of farmers in that area and with the cost of diesel this year, they had a tremendous financial burden.”
Parsons said she wasn’t sure when the tender for the new bridge would be issued.
“It’s supposed to go out so that it’s ready to start next spring,” she added. “But it will take time to get everything in place because they are shifting the road over to accommodate entrance onto the new structure.”
Highway 106 detour
Parsons also announced that the closure of Highway 106 between Dorchester and Memramcook has been extended until the end of March.
The work involves installing a culvert beneath both the highway and the CN railway tracks, but Parsons said workers “ran into an issue with the shoring that they’re using to stabilize the tracks.”